Bekendtgørelse om indgået kontrakt · 15. februar 2024

CPH City & Port I/S’ (Udviklingsselskabet By & Havn I/S’) public procurement procedure concerning Shoreside Power Supply 2023

Udviklingsselskabet By & Havn I/S offentliggjorde 15. februar 2024 en bekendtgørelse om indgået kontrakt om »CPH City & Port I/S’ (Udviklingsselskabet By & Havn I/S’) public procurement procedure concerning Shoreside Power Supply 2023«. Den anslåede værdi er 140.000.000 kr. Den samlede kontraktværdi er 225.017.968 kr. Kontrakten er tildelt PowerCon A/S.

Type
Bekendtgørelse om indgået kontrakt
Ordregiver
Udviklingsselskabet By & Havn I/S
By
København K
Offentliggjort
15. februar 2024
Kontrakttype
Varer
Procedure
Udbud med forhandling uden forudgående offentliggørelse
Anslået værdi
140.000.000 kr.
Kontraktværdi
225.017.968 kr.
CPV-koder
31000000, 31170000, 31174000, 31320000, 31340000, 71320000
Udførelsessted (NUTS)
DK011
TED-nummer
95279-2024

Beskrivelse fra ordregiveren

CPH City & Port I/S’ initiated this tender procedurement concerning Shoreside Power Supply, SPS. The Shoreside Power Supply is to supply Oceankaj and Langeliniekaj, two quays situated in the port of Copenhagen, with the converter situated at Oceankaj. The project includes the complete design, deliverance and execution of a converter station incl. isolations transformers, shoreside power distribution, cable management systems (Shoreside Power System, SPS) incl. any necessary connection boxes, which will connect with a shore power supply for cruise ships calling at both Oceankaj in Nordhavn and Langeliniekaj in Copenhagen Inner Harbour. The Supplier shall as a turnkey Supplier be responsible for and perform the complete design, including Design management and ICT management, and execute all turnkey supply services (hereinafter referred to as the “Services”). The Design and Supply Contract has the following options (“Options”), cf. section 6 of the Design and Supply Contract. • Option 1: Additional frequency converter capacity needed to reach a total capacity of at least 48 MVA measured as a sum at the ship connection plugs. The added frequency converters and their auxiliary equipment shall have same specifications as the equipment supplied in the basic scope. • Option 2: One additional mobile cable system crane, rated to 16 MVA, available at Oceankaj with possibility to connect to any of the shore side terminal boxes O-T1, O-T2, O-T3. The additional mobile cable system crane vehicles shall have same specifications as the equipment supplied in the basic scope. • Option 3: The Service & Maintenance Agreement has a duration of 2 years with an option to increase with a duration of 1 year for three times, i.e. af total duration for up to 5 years.

Vinder af kontrakten

Andre bekendtgørelser fra Udviklingsselskabet By & Havn I/S

Kilde

Bekendtgørelsen er offentliggjort i TED (nr. 95279-2024). Teksten er ordregiverens egen. Udbudsmaterialet og eventuelle rettelser findes hos ordregiveren eller i TED. Genbrug med kildeangivelse (Kommissionens afgørelse 2011/833/EU).