Bekendtgørelse om indgået kontrakt · 9. november 2026
Competitive procedure with negotiation concerning West Bridge Bearing Refurbishment (WBBR)
A/S Storebælt offentliggjorde 9. november 2026 en bekendtgørelse om indgået kontrakt om »Competitive procedure with negotiation concerning West Bridge Bearing Refurbishment (WBBR)«. Den anslåede værdi er 42.500.000 EUR. Den samlede kontraktværdi er 39.789.644 EUR. Kontrakten er tildelt MT Højgaard Danmark A/S.
- Type
- Bekendtgørelse om indgået kontrakt
- Ordregiver
- A/S Storebælt
- By
- København V
- Offentliggjort
- 9. november 2026
- Kontrakttype
- Bygge- og anlægsarbejder
- Procedure
- Udbud med forhandling
- Anslået værdi
- 42.500.000 EUR
- Kontraktværdi
- 39.789.644 EUR
- CPV-koder
- 45221119, 44212120, 45221100, 45221110, 45223210, 45223500
- Udførelsessted (NUTS)
- DK022
- TED-nummer
- 777538-2026
Beskrivelse fra ordregiveren
The Contracting Entity calls for the tender for West Bridge Bearing Refurbishment (WBBR). The project involves refurbishment of 188 structural bearings on the West Bridge, which is part of the Great Belt Link in Denmark. The work includes both the provision of newly manufactured bearings (approx. 44) and the renovation of the remaining bearings over a period of maximum 5 years. The project involves two parallel concrete bridges – one for rail and one for road. The bridges have now been in service for well over 25 years and the service life of the PTFE sliding plates in the bearings are now close to the end of expected lifetime. The project comprises of substantial work above open waters and includes the handling of structural bearings with a weight between 5 and 8 tonnes. The work also includes design and manufacturing of temporary structures necessary to carry out the refurbishments, according to a concept developed by the Contractor. The bearings needing renovation will have to be taken to land for refurbishment. Pursuant to section 49 of the Danish Public Procurement Act, the Contracting Entity has further considered whether the Contract can be divided into other lots but has found it most appropriate not to make such a division. It is the Contracting Entity's assessment that dividing the Contract into lots would result in disproportionate administrative burdens, both in relation to the synergies, the tender process and in relation to ongoing contract management, including the ongoing management of the tasks under the Contract.
Vinder af kontrakten
- MT Højgaard Danmark A/S CVR 12562233
Andre bekendtgørelser fra A/S Storebælt
- Udbud af Hovedentrepriseaftale for Opgradering af havne A/S Storebælt · 28. oktober 2026
- Competitive procedure with negotiation concerning West Bridge Bearing Refurbishment (WBBR) A/S Storebælt · 16. januar 2026 · ca. 42.500.000 EUR
- Purchase of jet fans for the tunnel at the Great Belt Link A/S Storebælt · 15. december 2025 · 21.127.600 kr.
- Competitive procedure with negotiation concerning West Bridge Bearing Refurbishment (WBBR) A/S Storebælt · 4. december 2025 · ca. 42.500.000 EUR
- Udbud af Kontrakt om stålkonstruktioner til udskiftning af Storebæltsbroens hængere A/S Storebælt · 15. oktober 2025 · frist 19. november 2025
- Udbud af Kontrakt om fremstilling og levering af kabelplatform til Storebæltsbroen A/S Storebælt · 13. juni 2025 · frist 28. august 2025
Kilde
Bekendtgørelsen er offentliggjort i TED (nr. 777538-2026). Teksten er ordregiverens egen. Udbudsmaterialet og eventuelle rettelser findes hos ordregiveren eller i TED. Genbrug med kildeangivelse (Kommissionens afgørelse 2011/833/EU).