Bekendtgørelse om frivillig forudgående gennemsigtighed · 29. juli 2024
Refurbishment of converter transformers on Skagerrak 3
Energinet Eltransmission A/S offentliggjorde 29. juli 2024 en bekendtgørelse om frivillig forudgående gennemsigtighed om »Refurbishment of converter transformers on Skagerrak 3«. Den samlede kontraktværdi er 2.700.000 EUR.
- Type
- Bekendtgørelse om frivillig forudgående gennemsigtighed
- Ordregiver
- Energinet Eltransmission A/S
- By
- Fredericia
- Offentliggjort
- 29. juli 2024
- Kontrakttype
- Varer
- Procedure
- Udbud med forhandling uden forudgående offentliggørelse
- Kontraktværdi
- 2.700.000 EUR
- CPV-koder
- 50700000, 50711000
- Udførelsessted (NUTS)
- DK021
- TED-nummer
- 454314-2024
Beskrivelse fra ordregiveren
Energinet needs to refurbish the existing converter transformers on Skagerrak 3 in station Tjele. Skagerrak 3 HVDC connection was delivered by ABB in 1993. The AC, DC, and neutral bushings on the converter transformers needs to be replaced/retrofitted with SF6-free or gel-type composite bushings. Flanges, gaskets, and seals needs to be exchanged on the bushings and conservator. Additionally, accessories such as valves, new gas-relay, new thermometers, new pressure relays on transformers and tap changers, new oil level indicators, including new cabling for all former mentioned items, and exchange of rubber bag in the conservator needs to be exchanged. The refurbishment work that will require outages shall be done somewhere within the period 01.09.2026-30.11.2026 where it will be possible to take SK3 out of operation. Exact dates for outage shall be coordinated and agreed upon with Energinet and coordinated with Statnett. It is Energinet's assessment that the lifetime extension of the transformers requires deep insight and expertise in similar transformers with regard to service inspections, repairs and similar tasks, and that solving the task will require that the supplier will be able to procure the necessary spare parts for this purpose that are compatible with the components of the existing transformers. Energinet has published a prior notification no. 390064-2024, but no one has approached and shown interest. On that basis, it is Energinet's assessment that there is a legal basis for direct allocation of the contract in accordance with Article 50, litra b), ii), and e) of Directive 2014/25/EU. Energinet intends to award the contract to Hitachi Energy Demark A/S, who has taken over the production and delivery of the mentioned equipment. The contract will be awarded after a standstill period of ten days, calculated from the day after the publishment of this notice.
Andre bekendtgørelser fra Energinet Eltransmission A/S
- Anlægsentreprise ny Transformerstation Mesballe (MES) Energinet Eltransmission A/S · 6. november 2026 · 33.535.000 kr.
- Entreprisekontrakt om udførelse af bygge-og anlægsarbejder på Station Lyngerup og Station Ølstykkegaard -25/12717 - 23/03693 Energinet Eltransmission A/S · 5. november 2026 · ca. 70.000.000 kr.
- 26/05837 - Call for tender under the SQS 239894 - Cat. 2 - Procurement of site investigations subsea cables nearshore Bornholm Energinet Eltransmission A/S · 26. oktober 2026 · 2.451.265 EUR
- 22/06127 -Anskaffelse af bygge- og anlægsarbejder for etablering transformerstation Haslev Øst Energinet Eltransmission A/S · 9. oktober 2026 · 36.978.000 kr.
- Re-tendering - Framework agreement: Purchase of fittings for glass insulator strings 26/17723 Energinet Eltransmission A/S · 5. oktober 2026 · ca. 12.684.564 EUR
- Framework agreement - Purchase of fittings for glass insulator strings - 26/17723 Energinet Eltransmission A/S · 2. oktober 2026 · ca. 12.684.564 EUR
Kilde
Bekendtgørelsen er offentliggjort i TED (nr. 454314-2024). Teksten er ordregiverens egen. Udbudsmaterialet og eventuelle rettelser findes hos ordregiveren eller i TED. Genbrug med kildeangivelse (Kommissionens afgørelse 2011/833/EU).