Electrical installations required for connection of Battery Energy Storage System (BESS)
Ørsted Bioenergy & Thermal Power A/S offentliggjorde 24. februar 2026 en bekendtgørelse om indgået kontrakt om »Electrical installations required for connection of Battery Energy Storage System (BESS)«. Den samlede kontraktværdi er 9.833.637 kr. Kontrakten er tildelt Kemp & Lauritzen A/S.
- Type
- Bekendtgørelse om indgået kontrakt
- Ordregiver
- Ørsted Bioenergy & Thermal Power A/S
- By
- Fredericia
- Offentliggjort
- 24. februar 2026
- Kontrakttype
- Bygge- og anlægsarbejder
- Procedure
- Udbud med forhandling
- Kontraktværdi
- 9.833.637 kr.
- CPV-koder
- 45310000
- Udførelsessted (NUTS)
- DK012
- TED-nummer
- 127555-2026
Beskrivelse fra ordregiveren
As part of the AVV Square 2.0 Project a Battery Energy Storage System (BESS) shall be installed within the perimeters of the power station Avedøreværket (AVV), located in Avedøre (Hammerholmen 50, 2650 Hvidovre), Denmark. The BESS shall be integrated in the existing 11.5 kV system of the power station Avedøreværket with connection to the Point of Connection in Installation of BESS (PCI). The electrical installations between the BESS and the PCI shall consist of the following components and systems: a) BESS internal cabling between the BESS equipment units b) Cabling between the BESS and the PCI c) Cabling for communication between the BESS and the existing DCS (Distributed Control System) of AVV d) Cabling between BESS MV Switchgear and DCS & auxiliary power supply e) Cabling between Main MV Switchgear and transformer differential protection relay f) MV cable terminations g) Bonding system of MV cables incl. required equipment such as Earth Continuity Conductor (ECC – if required), Sheath Voltage Limiters (SVL – if required), link boxes (if required) h) Connection of cables to BESS MV switchgear i) Connection of cables to feeder for BESS connection at Main MV switchgear j) MV protection setting study and testing of MV protection system after installation k) Auxiliary Power Supply connection for BESS MV switchgear l) Earthing and bonding of systems and components m) Lightning Protection System n) Cable installation on cable bridges, ladders and trays including required installation material (cable bridges, ladders and trays, cable cleats) o) Cable installation (buried) in trenches and ducts p) The scope of supply includes provision of all cables including but not limited to approximately 4500 meters of 11.5 kV power cables - 1x800 mm² Al XLPE q) The scope of supply also includes: Installation and commissioning of the electrical installations as defined above at the power station Avedøreværket, located in Avedøre (Hammerholmen 50, 2650 Hvidovre), Denmark.
Vinder af kontrakten
- Kemp & Lauritzen A/S CVR 57471719
Andre bekendtgørelser fra Ørsted Bioenergy & Thermal Power A/S
- Udbud af Rammeaftale for service og køb af hejse- og løftegrej Ørsted Bioenergy & Thermal Power A/S · 5. november 2026 · ca. 15.000.000 kr.
- BIO_Farvandsafmærkning_26-32_PA Ørsted Bioenergy & Thermal Power A/S · 9. oktober 2026 · 22.090.740 kr.
- Framework agreements for Hydraulic Services and Wear Parts Ørsted Bioenergy & Thermal Power A/S · 1. oktober 2026
- Supply of Ammonia (99,5%) and Ammonia Water (24,5%) Ørsted Bioenergy & Thermal Power A/S · 19. august 2026
- DK_Elydelser_26-34_FA Ørsted Bioenergy & Thermal Power A/S · 22. juli 2026 · ca. 218.000.000 kr.
- BIO_Stevedoreydelser_26-31 Ørsted Bioenergy & Thermal Power A/S · 25. juni 2026 · 294.905.415 kr.
Kilde
Bekendtgørelsen er offentliggjort i TED (nr. 127555-2026). Teksten er ordregiverens egen. Udbudsmaterialet og eventuelle rettelser findes hos ordregiveren eller i TED. Genbrug med kildeangivelse (Kommissionens afgørelse 2011/833/EU).